Preliminary designs are carried out to determine the optimal technical solution for the project and to define a budget and a schedule for the studies and the execution.

SENTEC ING. carries out preliminary designs according to the accuracy required by the customer, as this pre-study aims to understand as best possible the following part of the project relating to technical requirements, budget and schedule.

phase de projet 2

Basic Engineering Design

Basic Engineering Design Services

  • Definition of the objectives for the project jointly with the customer
  • Determining the major modifications to carry out, highlighting the technical requirements to reach the objectives
  • Definition of the main materials for the project
  • Comparison of several technical solutions
  • Consideration of the regulatory requirements

Examples of deliverables

  • Note technique de synthèse d’avant-projet sommaire
  • Réquisitions techniques de matériels génie chimique, équipement chaudronné ou instrument
  • PID et UID projets
  • Plans de principe d’implantation et d’isométrie
  • Logigramme de fonctionnement, schémas explicatifs de fonctionnement
  • Planning prévisionnel d’études, planning prévisionnel de projet
  • Budget + / – 30%

Front end Engineering Design

Front end Engineering Design

  • Confirmation of the objectives of the project relating to production, safety, quality, regulation, ergonomics…
  • Determining all the technical modifications that allow to reach the objectives
  • Determining the technical details relating to design
  • Consideration of the installation requirements relating to the equipment, skid or other units
  • Pre-consultation with suppliers

Examples of deliverables

  • Technical data sheet relating to the front end engineering design
  • Technical requisitions for chemical engineering materials, tank or instruments, form for consultation with suppliers
  • Detailed PID and UID projects
  • Layout study for critical equipment or pipes
  • Inventory of materials, equipment, valves, pipes (listing)
  • General principles for the functioning of new installations
  • Safety matrix
  • Utility balance
  • Waste balance
  • Detailed schedule for the studies
  • Detailed schedule for the project
  • Budget +/- 20%

Our fields of Activity

Sentec Ing supports you throughout your projects, from the initial feasibility stages to the technical reception and commissioning of the new installations.
We offer support and technical expertise, tailored to your needs, on all our missions.

Chemistry

Petrochemistry

Fluids

Agro-Food

Pharmaceutical

Energies